Home
Restoration Plan
Public Engagement
News
Project Updates
Health and Safety
Photo Gallery
Public Documents
Ask a Question
Sign Up for Newsletter
SEARCH:
Consolidation Area Water Treatment Plant
Aerials
Lakeshore Activities
FMA Live!
Barrier Wall Construction
Pipeline Progress
Consolidation Area
Sportsmen's Day
Honeywell Institute of Ecosystems Education
Honeywell Summer Science Week at the MOST
Shrub Willows
LCP Wetland Restoration
Willis Avenue Groundwater Treatment System
Solvay-Geddes Community Center
Reed Webster Park
Discovery Day at the MOST
Nine Mile Creek
Onondaga Lake Data Collection
Former LCP Site
Consolidation Area
May 2011: Preparation to Build the Consolidation Area Begins with Roads and Containment Berms
August 2011: Construction of the Containment Area (Background) and Water Treatment Plant Continued Throughout 2011
September 2011: Containment Berms and Anchor Trenches Surround the Consolidation Area
Air Monitoring and Regulatory Oversight
November 2011: Air Quality is Constantly Monitored at Eight Monitoring Stations Around the Perimeter of the Site. All Data is Sent and Reviewed in Real-Time at the Air Monitoring Command Control Center.
Click Here for More Information
November 2011: Air Monitoring Results are Posted on the Website and Show the Locations of the Fixed Monitors
2011: The Air Monitoring Program, Started in 2010, Continues During All Phases of Construction and Operation
November 2011: The New York State Department of Environmental Conservation Maintains a Field Office on Site
Building the Clay Layer
May 2011: Clay is Delivered to the Consolidation Area to Begin Construction of the Impermeable Clay Liner
May 2011: A Quality Control Technician Samples Clay for Laboratory Analyses
June 2011: Construction Equipment Uses GPS to Place the Impermeable Clay Base Layer
June 2011: The Clay is Mechanically Compacted with a Vibratory Roller
September 2011: Quality Control Engineers Inspect Placement of the Clay Layer Using GPS Technology
September 2011: A Quality Control Technician Uses a Core Sampler to Test the Clay Layer for Permeability
Installing and Testing the Liner
May 2011: High-Density Polyethylene (HDPE) Liner is Delivered for Installation at the Containment Area
August 2011: Each Roll of Liner Weighs Approximately 4,000 Lbs
August 2011: Liner Forms the Second Impermeable Layer, Installed Above the Clay Layer. Orange Sand Bags Temporarily Hold the Liner in Place
September 2011: High-Density Polyethylene Liner is Deployed Over the Impermeable Clay Layer
September 2011: Quality Assurance Engineers Monitor Settlement Within the Containment Area
October 2011: Technicians Inspect and Test the Liner After Installation
October 2011: Sections of the Liner are Sealed Together Using a Welder
October 2011: Technicians Perform Testing of the Liner, Which is Secured in the Trenches
October 2011: A Vacuum Gauge is Used to Test the Welded Seams of the Liner
October 2011: Technicians Collect Liner Samples for Testing. A Worker Seals a Patch Over a Sampled Area
October 2011: The Size of the Containment Area will be Equivalent to 45 Football Fields in Area
Placing the Gravel
September 2011: After Installation of the Liner, Gravel is Placed on Top
September 2011: Spotters Assist with Placement of the Drainage Gravel Over the Liner
October 2011: The Gravel Layer Helps Facilitate Water Drainage
Constructing the Water Treatment Plant
September 2011: Pipes are Installed to Transport Water from the Containment Area to the Water Treatment Plant
September 2011: Construction of the Water Treatment Plant Started in 2010; It Will Treat the Water Drained From Geotubes Within the Containment Area
November 2011: Installation of the Water Treatment Tanks and Pipes Will Continue Throughout the Winter Months